Friday 17 December 2010

T.S. Resolute (almost) Complete

Trimline (the interior fit-out contractors) finished work on the Resolute this week, so, except for a few odds and ends that need finishing off, the ship is complete, which is amazing news, and marks the near completion of a project that has stretched over 3 years, and cost over £1,000,000.
However, there is still a lot more work to do before the project is over, and the first group arrives in just over 3 months time...
  • The site at chidham needs a massive amount of work completing, re-landscaping the sea wall, laying hundreds of square metres of new turf, and laying wooden decking on the side decks of the ship to name just a few of the Jobs.
  • we need to fit the ship out with tables, chairs, bunks and all sorts of other items, which will make it complete
  • we have raised about 90% of the cost of the project already, and have temporary funding secured to allow us to complete the ship in time, but still need to raise about £130,000.
  • and much more...
If you feel you could Help us out finishing the project off, please get in touch, we are looking for volunteers to help us out with a wide variety of jobs, so If you'd like to get involved, whatever your skills are, whether your a photographer, a cook, a joiner or a physicist, get in touch with me at the centre on 01243 573375 and I'm sure there will be something you can get involved with, we will be running several volunteer days and weekends throughout the spring, or alternatively, if your free during the week, there are always jobs around that we would love the help with.

we'll try to get more pictures up here next week, but in the meantime, there's a slide show of the interior of the ship below, and if you can't wait to come down and see it for yourself, give us a ring and I'm sure we'll be able to show you round.

Saturday 11 December 2010

IT GETS WORSE BEFORE IT GETS BETTER!




The jetty is now a challenge to jump- No one has tried it yet!!


Unfortunately we have found a seriously rotting cross member that needs replacing with a steel beam, which has delayed us. In the meantime we have turned to groundworks preparation including the entrance way.
The site has been badly affected by all the machinery and needs restoration
Alongside all this Trimline are finishing off the fitting out and contractors on all over the ship like ants.

The delay to the jetty means that the borehole drilling and service connections are pushed back to mid January.

We are still on target to have Resolute in use next season. although there is still an awful lot to do.


Norman Doney
Executive Director

Wednesday 1 December 2010

JETTY REPAIR UNDER WAY




As if we weren't trying to do enough, alongside RESOLUTE works we are having the field to ship gangway section of the 40 year old jetty repaired. This section was indentified as in need of repair earlier in the year. We are very grateful to The Veolia Trust who have provided funds to enable this work to be done. The work will take us up to Christmas and will greatly extend the life of the jetty. All ship services will then be run alonside the repaired section in the new year.
Norman Doney
Executive Director


Tuesday 30 November 2010

TS "Resolute" has been in her new home for about four weeks now, with the last two weeks properly moored. After the excitement of moving two ships and overcoming many problems in weather and tugs, the fitting out process seems almost mundane with not a lot to report.

However, it is proceeding apace and the doors are bing fitted to the cabins and possibly carpeting will go down this coming weekend. The cabins will then look really good and ready to fit the beds. I will try and send photos in a future blog.

Nearly all the ceilings are now finished. A lot of light fittings are in place. A big step forward today was a very successful meeting with the suppliers of the heat pump and solar panels where a big problem of location of solar panels seems to have been resolved. They will go on the wheelhouse roof where no-one will see them except the birds. Let's hope they do not decide to ... you know what. In addition to the activity on the ship, the jetty is undergoing repair which will take about three weeks and we cannot make all the connections until that is finished.

The ship looks like it is in the later stages of completion which, according to folk law of normal shipyards, looks in a terrible mess. In a very short time now, all will be cleaned up and ready to hand over to CYE except that nothing will work until the New Year because of the jetty work. Oh well, can't have everything.

In parallel with the fitting out of the new ship I am being fitted out with a new hip, but not by Trimline. So it is new Ship -new Hip. I will be not visiting the ship for a bit and Norman will be Project Managing until I can pick up some duties again.

Oh, forgot to mention the photograph. It may have been included in a previous blog but it is such a good one of her in her now home that I have reproduced it in slightly larger format on it's own.

If perchance you have photos of the ship, please send a disk to the Sailing Centre for the attention of Ben Ritchie.
David Edwards

Friday 19 November 2010

Starboard gangway and electrical connection.



Today, electric power has been connected to the ship. It is a three phase cable and tracked accross the aft mooring strut. This will enable Trimline to re-commence fitting out with plenty of power for machines and lighting where necessary.

The last picture shows Kevin, our Maintenance Manager, putting the finishing touches to the ropes which hold the cable to the strut. It is low tide and the ship is on the mud. with a slight list to port but level fore and aft. The reed grass is covered every high tide and will be well over a metre of water at Spring tides. Once the jetty is repaired, the cable will be tracked back along the jetty and suspended under the new aft gangway (which can be seen on the jetty awaiting installation).

The top picture shows the new gangway jacked up from the temporary one which, in turn, rests on the temporary pontoon. This is to enable the bracket to be designed, fitted and welded to the deck to take the permanent starboard gangway.

Next week, we should have a full crew plus subcontractors on board.

David Edwards Project Manager.

Thursday 18 November 2010




After getting the mooring struts and cables in place yesterday, the starboard gangway was placed in position. It is 11 metres long and weighs in at 2.7 tonnes even though it is aluminium construction.

The digger did not have enough reach to get it to the ship so it was slid up the temporary gangway by Robin, James and Kevin. This was a difficult operation but skillfully carried out. It is resting on the ship and tied with ropes and needs permanent fixing. However, even with the temporary attachment, it is safe for use and is the only means of access to the ship.

The aft gangway (only 5 metres long) will not be fitted until the jetty is repaired but the gangway is already on the further part of the jetty in readiness. Both gangways will be wheelchair accessible.

David Edwards, Project Manager

Wednesday 17 November 2010

TS Resolute, a work in progress





The pictures posted on 7th November were identified correctly by Steve Band and you should be able to see the results on the comment box for that day. Well done Steve! Steve has had a long association with CYE Sailing Centre and his knowledge of the Chichester Harbour enabled him to come up with the right locations. The picture of the ship being towed in the harbour with Hayling Island in the background may have been the most difficult to identify.

The ship is now moored permanently. The pictures above (all at low tide) show;

View from lower end of jetty.

Pontoon used to increase safety of temporary mooring during strong winds.

Jetty repair work just commencing

Final mooring system of struts are now in place. Most of the ropes will be removed later, leaving just a few onto the sea wall as additional safety measure.

As you will see, the ship is very much a work in progress on the outside. Interior fitting out was interrupted for the tow and mooring system, but will re-commence next week.

David Edwards Project Manager.


Tuesday 9 November 2010

Work at the CYE site at Chidham




This week is a hive of activity.

The site at CYE is turned into a construction project with lots of mud, diggers, dump truck etc.

The mooring struts arrive by truck from Walcon Marine.

The two gangways arrive all the way from the Tyne on the North East coast.

The mooring wires are being fixed to the ship ready to be attached to mooring frames on shore.

The fitting out of the ship is on hold for several days until it is properly moored, but should re-commence by Trimline sometime next week.

David Edwards. Project Manager

Monday 8 November 2010

WORK CARRIES ON











Yes after all the excitement of the safe arrival of RESOLUTE on Saturday, work started today on preparations for final commissioning and asociated site works.




Lots of machinery and deliveries of stones arrived too.




David Edwards supervised the placing of the mooring frames and wires which will have struts attached to secure the ship in place. Later this week 450mm diametre holes will be drilled down through the sea wall and filled with steel and concrete to hold the frames in place. Further mud levelling work will continue this week too. Meanwhile while Kevin Nash and Nick (the Kog) Pyke organised a work party preparing a drained Rib storage area which is currently boggy whenever it rains.


Norman Doney

Sunday 7 November 2010

Resolute is home













The good ship "TS Resolute" left Portchester on November 5th at 11 am and was towed by a tug and guided by a second tug to Camber Dock, just inside Portsmouth Harbour. We were tied up right opposite the IOW car ferry for the night and Norman, David and Charlie slept on board with two dogs as guard against intruders.
Next day, November 6th, the tugs arrived at 7 am for the tow to Chichester. and in the morning there was almost no wind. The tow to Chichester took 2 hours. Once inside the harbour a crew was transferred from the centre RIB to Resolute, and then another smaller tug and a very large RIB took over for the final leg up the Bosham channel to destination. Then the sun came out for some wonderful photos! The weather was a miracle, because there were gales the week before and gales are forecast for Monday. Does God arrange the weather? He has in the past and so He did this time too.
Resolute was nudged into its berth (after several minutes resolutely stuck in the mud bank) and then she was pulled and pushed into place by several boats and shore ropes manned by a shore crew.
She does look good in her new home. Lots more pictures are to come so keep watching.
There is lots of work to do this coming week and right up to Christmas and beyond, but Resolute is HOME.
Guess where each picture is taken and post the results with a comment. The first person to come up with five correct answers will get a mention in despatches, plus a VIP tour of the ship.
(Those closely involved in the exercise are excluded)
David Edwards and Norman Doney


Wednesday 3 November 2010

GD Pictures and update on new ship




The Gerald Daniel at her new home
off Chelsea Embankment.
















The Gerald Daniel under Chelsea Bridge (so we think) on her way on the night of arrival, 22nd October 2010.

















A dramatic photo of the Gerald Daniel about to pass under the famous Tower Bridge in the heart of London.

She is on her way to Chelsea.















Another historic photo of the Gerald Daniel in front of Big Ben, the most famous clock in the world.

The houses of parliament are in the background.



Published by David Edwards, Project Manager.

Post Script. The new ship is now empty of all Trimline workers and is prepared for the tow to Chichester harbour. This is planned for Friday or Saturday 5th or 6th October depending on weather and could be postponed to Monday or Tuesday 8th or 9th October. However we think it most likely to be towed this Saturday 6th October.

Watch this space for some (hopefully) very dramatic photos of the new ship under tow and arrival at Chidham. Once at Chidham, we have planned an extensive work program of mooring, finishing the fitting out, attachment of gangways and connecting up all the services. More on this in future Blogs.

David.

Sunday 31 October 2010






The mooring frames arrive by truck. These frames will be laid on the land side of the sea wall
and will be used to attach struts from the ship.

They are very heavy and will be concreted in place with steel reinforcement.

The field was not thought to be hard enough to take a 32 ton truck so offloading was done with a hydraulic arm (with radio remote control) from just inside the main entrance gate to the CYE site.

The frames will be moved over to the sea wall with a caterpillar tracked digger during the next week.

David Edwards

Thursday 28 October 2010

NORMAN ON RADIO SOLENT
Julian Clegg had his normal catch up with Norman, at 6:45 this morning on Radio Solent. With the staff on their 300mile bike ride and the GD leaving its berth and being towed up the thames this week (see the pictures further down this blog) there was a lot to talk about.

Click here to listen to the interview (3.8MB MP3 file)
It's a big file so please be patient while it downloads before it starts playing.

Tuesday 26 October 2010

FITTING OUT PROGRESS





Corridor walls on lower deck now fitted and some door frames going in.










An extractor fan in the ceiling of the disabled toilet.











I hope the electrician knows where all these wires go!












One of the ceiling lights in the main deck.





It is now only a week to ten days before the ship is moved from Portchester to Chichester Harbour. We have a window of opprtunity of about 6 days to have a suitable tide and suitable weather and the forecast does not look good at the moment.

David Edwards Project Manager

Arch to Angel


10 intrepid cyclists from CYE are cycling from the Marble Arch, in london, up to the angel of the north, covering 300 Miles in 4 days, to raise money for the new ship, if you'd like to support them visit:
or to watch their progress visit:
where Kevin will be blogging throughout the ride, from a support viecle.

Saturday 23 October 2010

Gerald Daniel's night out in London




After nearly 40 years in the Chichester berth, The Gerald Daniel finally had a chance to go to London! After an excellent journey round the coast, in a short period of suitable weather, she glided up the Thames. She went under Tower Bridge at 10pm on Friday evening and on to Cadogan Peir next to Albert Bridge at 11pm. She is now resting at her new home with a view of Battersea Park. I was there to watch part of the journey and see her into her new home.



Norman Doney Executive Director


Friday 22 October 2010





Another major navigation mark (milestone for landlubbers!) for CYESC. After two weeks on a buoy in the harbour, having left a large hole in the mud (picture in previous blog) the good ship "Gerald Daniel" is on her way to a new watering hole (pastures new?). The tug Christine arrived at 12 Noon on Thursday 21st October and departed again in less than an hour with the GD going lickety split down the harbour and out to sea. We followed in Ribs but the longboat crew did not have a chance to keep up. At time of writing, the GD is just off Margate with the tug at anchor and will be on her way up the Thames, past the Houses of Parliament and the London Eye, under tow with a smaller workboat with less airdraft to get under the bridges. She is scheduled to arrive at Chelsea near the Albert Bridge at midnight Friday night and Norman plans to be there to meet her and the new owner with a final hand over of ownership.

What a wonderful day! There were many obstacles in the way with tug breakdown, unsuitable weather etc. but it has now happened. The CYE team and team spirit has come out on tops yet again. Thanks to all. David Edwards Project Manager.