IT GETS WORSE BEFORE IT GETS BETTER!




The jetty is now a challenge to jump- No one has tried it yet!!


Unfortunately we have found a seriously rotting cross member that needs replacing with a steel beam, which has delayed us. In the meantime we have turned to groundworks preparation including the entrance way.
The site has been badly affected by all the machinery and needs restoration
Alongside all this Trimline are finishing off the fitting out and contractors on all over the ship like ants.

The delay to the jetty means that the borehole drilling and service connections are pushed back to mid January.

We are still on target to have Resolute in use next season. although there is still an awful lot to do.


Norman Doney
Executive Director