Saturday 18 September 2010

Patio doors and heating pipes

The patio doors are now fitted!
They are located in the Day Room and
once the ship is at Chidham there will be superb
views overthe water looking towards Itchenor.
They will face East and get the morning sun.

Underfloor heating pipes are now complete on the whole of the main deck and also the Wheelhouse. The floor contractor is now
working through the lower deck.

Next week, the mooring system brackets will be welded to the belting on the starboard side of the ship. These brackets will take struts, the other end of which will be attached to very heavy frames
on the sea wall. More details in due course.

David Edwards Project Manager