Some detail recent progress







Photographs on this blog show the aft staircase with open railing. This is in contrast to the forward staricase which is fully cased. Both comply with fire regulations. Also shown is the fire control panel being wired. This is immediately inside the aft entrance door. The fourth photo is the door between the aft entrance room and the corridor to the left of which is the staircase leading to the wheelhouse.

The pictures also show that the floor has now been screeded level ready for the vinyl final floor covering to be laid.

There is now only three weeks to completion before the ship is prepared for its tow to Chichester Harbour. Some finishing work will then be done for a final hand over which is expected to be at the end of November.

David Edwards Project Manager